Hunter Building Demolition

An external view of the Hunter Building, in black and white
East view of Griffith Duncan Theatre, Hunter Building

Project overview

Plans are underway to demolish the Hunter Building, Bowman Building, Wonnayba Child Care, and the Special Education Building at the University of Newcastle’s Callaghan Campus, with works due to commence in 2027.

The Hunter Building has been planned for demolition since 2020 when a feasibility study determined due to its age, condition, and contamination, it was deemed end-of-life.

The demolition of these buildings will be a carefully staged process, adhering to the best practice standards for demolition works, and working closely with SafeWork NSW.

The first phase will focus on the internal strip-out of the building. Students and staff will be unlikely to notice any changes until the second half of 2027, when the external structure will start to be dismantled.

There are no plans yet for the future of the site. The demolition will create space for new opportunities that will help shape the future of our Callaghan Campus.

Safe demolition

Measures will be put in place to ensure all demolition activities are conducted safely, with minimal risk to the university community. These include:

  • External air monitors to detect any presence of hazardous materials throughout the demolition process.
  • A WHS consultant appointed to review safe work methodologies and ensure compliance with best practice standards.
  • An occupational hygienist engaged to assess contractor methodologies, advise on exclusion zones, and confirm appropriate management measures.
  • A traffic consultant will review pedestrian and vehicle movements to inform the Construction Traffic Management Plan.
  • Hard hoardings will be erected to prevent unauthorised access to the demolition site.
  • Safe and suitable pedestrian paths, including street lighting and CCTV, will be established for staff and students, particularly between the Student Accommodation and key campus areas, including Bar on the Hill and the Forum.

History of the building

The Hunter Building was constructed in 1974 for the Newcastle Teachers College. It was acquired by the University of Newcastle in 1989 following an amalgamation with the Hunter Institute of Higher Education.

In addition to serving as the largest teaching building at Callaghan for 50 years, it was also home to the Griffith Duncan Theatre, a beloved space for learning and performance.

Many alumni, staff and the broader community feel a strong connection to the Hunter Building, and the University will honour its legacy in the lead up to its demolition.

Program updates

  • December 2020 – Hunter Building closed after a study reveals it requires major repairs and contained deteriorated asbestos. Read more.
  • September 2025 – V Building named Griffith Duncan Building to honour the legacy of Newcastle Teachers’ College Founding Principal. Read more.
  • October 2026 – McMann Services appointed as contractor. Read more.